Lexton Community Hub

  • Project typeNew community hub building
  • Project value$3.8 million
  • Project scheduleThis project is now complete.
  • Contractor nameS J Weir
  • Completion Date31 January 2023
Lexton Community Hub.JPG

Lexton is on Dja Dja Wurrung Country.

 

The Lexton Community Hub is now open for business.

The Lexton Community Hub is newly built space with a multipurpose function room, change rooms, bar, canteen, and commercial kitchen for a range of community and sporting needs to replace the current outdated facilities.

Lexton is an unsewered township, so wastewater must be treated onsite with septic systems. The size of the Community Hub triggers the need for a 5000 litre per day treatment system. Systems this size must have Environment Protection Authority (EPA) approval before installation.

Arris Water Treatment and Technology was appointed in 2021 to create a design to meet EPA standards.

Discussions between Arris and the project manager were affected by many factors, including COVID-19 in 2021, which resulted in a delay to the completion of the design specifications. The specifications have been received and are awaiting formal acceptance by the EPA.

Once the EPA has approved the septic system for the Hub, construction is expected to commence in May. The estimated cost of the wastewater treatment system is around $200,000 which is a similar cost from the original quote. The total project cost is around $3.8M.

We know the hold up with the wastewater treatment system has meant a set-back in the handover timeframe and we apologise for the delay. We are looking forward to the Hub becoming a lasting asset for the Lexton community.

Project Funding:

Total Project Cost:      $3,835,921

 Source of Funds Amount
Victorian Government

$800,000

Commonwealth Government (BBRF)

$1,000,000

Commonwealth Government (LR&CIP)

$684,921

 Pyrenees Shire Council (Original budget)

Additional funds (Council approved 17 Aug 2021)

$421,000

$530,000

Community (Lexton Recreation Reserve COM)

(Committed Funds)

$200,000

($120,000)

Lexton Bushfire Recovery Grant (State)

$100,000

Lexton Bushfire Recovery Grant (Commonwealth)

$100,000

 

   

Location

Lexton Recreation Reserve, Lexton 3352  View Map