Burnbank - Floodways, Dovecot Lane - LRCIP4

  • Project typeFloodway Upgrade
  • Project value$50,000
  • Project scheduleAugust 2023 to December 2024
  • Completion Date31 July 2024

Burnbank is on Dja Dja Wurrung Country.

Works include improving the existing floodway by replacing undersized culverts and installing a permanent concrete deck and associated end walls.

The installation of a permanent 60mconcrete deck and associated end walls is designed to withstand future flood events.

UPDATE:

This project has now been completed 4 months ahead of schedule.

Before Photos:

Dovecott-Lane-Floodway-Before-Photo1.jpeg   Dovecott-Lane-Floodway-Before-Photo2.jpeg

Works Completed Photo:

Dovecott-Lane-Floodway-Completed-Works-Aug-2024.jpeg

 

 

  