Avoca crossing points

Published on 23 June 2021

Avoca_1390_screen.jpg

Crossing points in High Street, Avoca

Work is underway for the construction of four pedestrian crossings on High Street Avoca. Works commenced today (28/6) on the west side at Duke St outstand, contractors Fulton Hogan will continue along the west side until all four are complete then do all four systematically along the east side; then do the central median footpath links.

Traffic is down to one lane at 40kmh, we thank you for driving safely. 

Construction is expected to last about four-five weeks, weather dependent.